Legislation Details

File #: 26-414   
Type: Report Status: Agenda Ready
File created: 9/23/2026 In control: City Council
On agenda: 10/20/2026 Final action:
Effective date:    
Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR FY 2026 LOCAL STREET IMPROVEMENT PROGRAM, CIP PROJECT NO. 16322
Attachments: 1. Att. 1 - Resolution No. 26-171.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - Staff Report dated April 21, 2026 (without attachments).pdf, 4. Att. 4 - Location Map.pdf
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Submitted By: Public Works

Prepared By: Masako Hennequin, P.E., Senior Civil Engineer

 

Subject:

title

CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR FY 2026 LOCAL STREET IMPROVEMENT PROGRAM, CIP PROJECT NO. 16322

body

 

Summary:

The City Council is being asked to consider Resolution 26-171 and Notice of Completion for the FY 2026 Local Street Improvement Program (Attachments 1 and 2, respectively).  

 

Background:

On April 21, 2026, the City Council awarded a construction contract to All American Asphalt to complete pavement improvements on various local streets (Attachment 3). The contractor completed the following: crack filling, slurry sealing the full width of asphalt pavement, and re-striping on selected citywide residential streets and the City’s Water Reclamation Plant, as shown on the Location Map (Attachment 4).

 

 

After Construction

After Construction

     An estimated summary of the project expenditures related to this NOC is provided below:

 

                     Project Management / Admin                                                                                             $          2,271

                     Engineering Design                                                                                                                                          13,080

Construction Contract                                                                                                                                     565,951

Construction Management / Inspection                                                                                             35,440

                     Total                                                                                                                                                                                  $      616,742

 

 

Council Options:

•                     Adopt Resolution No. 26-171, which would accept the completed FY 2026 Local Street Improvement Program, CIP Project No. 16322.

 

•                     Modify and adopt Resolution No. 26-171.

 

•                     Continue the item with direction to provide additional information.

 

Environmental Review/Analysis:

This project was previously determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Class 1 (Existing Facilities, 14 CCR section 15301) of the State CEQA Guidelines.

 

Fiscal Impact:

The total project cost of $616,742 is within the approved project budget of $750,000 from the Gas Tax Fund, Account Number 012-861-45300-000-16322.

 

Potential Action(s):

recommendation

If the City Council concurs with the information provided within this staff report, moving this item without modifications would result in adoption of Resolution No. 26-171, which would:

 

1.                     Accept the FY 2026 Local Street Improvement Program, CIP Project No. 16322, from All American Asphalt;

 

2.                     Authorize the City Clerk to execute and record the Notice of Completion for the FY 2026 Local Street Improvement Program, CIP Project No. 16322;

 

3.                     Authorize the City Clerk to release the payment bond 35 days from the recordation of the Notice of Completion upon verification with the Engineering Division that no liens have been levied against the Contractor, All American Asphalt; and

 

4.                     Authorize the City Clerk to release the performance bond for this project upon receipt of a warranty bond in a form acceptable to the Public Works Director/City Engineer in the amount of 25% of the total construction cost.

 

end

Attachment:

1.                     Resolution No. 26-171

2.                     Notice of Completion

3.                     Staff Report dated April 21, 2026 (without attachments)

4.                     Location Map

 

Notification:

None.