Submitted By: Public Works
Prepared By: Niki Beach, Environmental Programs Analyst
Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE EL CAMINO REAL CORRIDOR RUNOFF TREATMENT PROJECT, CIP PROJECT NO. 26802
body
Fiscal Impact:
The total project cost of $410,293 is within the approved budget of $415,500. The project has also been previously authorized for grant funding under OCTA’s Tier 1 Environmental Cleanup Program and staff is in the process of requesting reimbursement for $323,834, which is 80% of the construction cost of $404,793.
Summary:
Before the City Council is a Resolution (Attachment 1) and Notice of Completion (Attachment 2) for the El Camino Real Corridor Runoff Treatment Project.
The project is part of a requirement by the California State Water Resources Control Board to install structural controls to capture debris down to 5mm in size, inclusive of all trash the size of a cigarette butt or larger, in high-traffic areas, such as multifamily developments and commercial areas, by 2030. City staff has identified 559 catch basins requiring retrofits, and with the completion of this phase, the City has retrofitted a total of 315 catch basins.
Background:
On May 20, 2025, the City Council awarded a construction contract to G2 Construction, Inc. (Attachment 3) for the installation of trash capture devices within 74 inlets in the locations shown on the map hereon.
The work consisted of mobilization and traffic control; catch basin cleaning; and custom design, fabrication, and installation of three types of devices. Upon closer investigation and troubleshooting by the City and G2, three catch basins in the original contract were determined infeasible for device installation at this time and were removed from the project. Each of the remaining 71 inlets received either a Connector Pipe Screen (CPS), Grated Inlet Trash Screen (GITS), or Automatic Retractable Screen (ARS) device, with several ARS devices installed on the curb face as an added layer of defense against trash reaching and potentially clogging a new CPS installed inside the catch basin.
Work was completed between May 22, 2025 and September 30, 2025. Below are representative photographs of the three device types installed.

A summary of the total construction expenditures is provided below:
|
Construction Management and Inspection |
$5,500 |
|
Construction Contract |
$404,793 |
|
Total Construction Cost |
$410,293 |
Council Options:
• Adopt Resolution No. 25-161 (Attachment 1), which would accept the completed construction work for the El Camino Real Runoff Treatment Project.
• Adopt Resolution No. 25-161 with modifications.
• Continue the item with direction to provide additional information.
Environmental Review/Analysis:
This project was previously determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Section 15301 of the state CEQA Guidelines, Class 1 (Existing Facilities, 14 CCR 15301).
Recommended Actions:
recommendation
Staff recommends that the City Council adopt Resolution No. 25-161---, which will:
1. Accept the El Camino Real Runoff Treatment Project, CIP Project No. 26802, from G2 Construction, Inc.;
2. Authorize the City Clerk to execute and record the Notice of Completion for the El Camino Real Runoff Treatment Project, CIP Project No. 26802;
3. Authorize the City Clerk to release the payment bond 35 days from the recordation of the Notice of Completion upon verification with the Engineering Division that no liens have been levied against G2 Construction, Inc.; and
4. Authorize the City Clerk to release the performance bond for this project upon receipt of a warranty bond in a form acceptable to the Public Works Director in the amount of 25% of the total construction cost.
end
Attachment:
1. Resolution 25-161
2. Notice of Completion
3. Staff Report dated May 20, 2025