Submitted By: Public Works
Prepared By: Masako Hennequin, P.E., Senior Civil Engineer
Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR ALLEY PAVEMENT REHABILITATION PROGRAM, CIP PROJECT NOS. 16316, 15316, AND 12305
body
Summary:
The City Council is being asked to consider Resolution 26-116 and Notice of Completion for the Alley Pavement Rehabilitation Program (Attachments 1 and 2, respectively).
Background:
On February 17, 2026, the City Council awarded a construction contract to Eagle Paving LLC for the Alley Pavement Rehabilitation Program (Attachment 3). Eagle Paving LLC completed construction of the 20-ft wide alley at the 100 block of Avenida Del Mar, as shown on the Location Map (Attachment 4). The project consisted of grinding and repaving the destressed asphalt pavement, removing and replacing deteriorated pavement areas, and constructing 707 LF of new four-foot-wide concrete alley gutter in the middle of the alley to improve drainage.
A summary of the total construction expenditures is as follows:
|
Project Number |
Budgeted Amount |
Expenditure Amount |
|
12305 |
$ 398,000 |
$ 153,088 |
|
15316 |
$ 100,000 |
$ 82,754 |
|
16316 |
$ 100,000 |
$ 84,999 |
|
Total Expenditures |
$ 320,841 |
Council Options:
• Adopt Resolution No. 26-116, which would accept the completed Alley Pavement Rehabilitation Program, CIP Project Nos. 16316, 15316, and 12305.
• Modify and adopt Resolution No. 26-116.
• Continue the item with direction to provide additional information.
Environmental Review/Analysis:
This project was previously determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Class 1 (Existing Facilities, 14 CCR section 15301) of the State CEQA Guidelines.
Fiscal Impact:
The total construction cost of $320,841 is within the approved budget for each respective project: Account Numbers 042-848-45300-000-16316, 042-848-45300-000-15316, and 042-848-45300-000-12305.
Potential Action(s):
recommendation
If the City Council concurs with the information provided within this staff report, the appropriate action would be to adopt Resolution No. 26-116, which would:
1. Accept the Alley Pavement Rehabilitation Program, CIP Project Nos. 16316, 15316, and 12305, from Eagle Paving LLC;
2. Authorize the City Clerk to execute and record the Notice of Completion for the Alley Pavement Rehabilitation Program, CIP Project Nos. 16316, 15316, and 12305;
3. Authorize the City Clerk to release the payment bond 35 days from the recordation of the Notice of Completion upon verification with the Engineering Division that no liens have been levied against the Contractor, Eagle Paving LLC; and
4. Authorize the City Clerk to release the performance bond for this project upon receipt of a warranty bond in a form acceptable to the Public Works Director/City Engineer in the amount of 25% of the total construction cost.
end
Attachment:
1. Resolution No. 26-116
2. Notice of Completion
3. Staff Report dated February 17, 2026 (without attachments)
4. Location Map
Notification:
None.