Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH ALLIANCE DIVERSIFIED ENTERPRISES FOR THE MARQUITA SLOPE INTERIM RECONSTRUCT PROJECT NO. 21208 AND UNENCUMBER FUNDS
Attachments: 1. Att. 1 - Res 26-117.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - 2025 Resolution for Award, 4. Att. 4 - Location Map PN 21208
Submitted By: Public Works
Prepared By: Shawn Ryan, Deputy Public Works Director

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH ALLIANCE DIVERSIFIED ENTERPRISES FOR THE MARQUITA SLOPE INTERIM RECONSTRUCT PROJECT NO. 21208 AND UNENCUMBER FUNDS
body

Summary:
The City Council is being asked to consider adopting Resolution 26-117 (Attachment 1), accepting the work performed by Alliance Diversified Enterprises, Inc., related to the Marquita Slope Interim Reconstruct Project, filing a Notice of Completion (Attachment 2), and unencumber $455,000 from the project account number 054-476-45300-000-21208 which will in turn increase the Sewer Depreciation Reserve Fund Balance.

Background:
On August 11, 2025, the City Council awarded a construction contract to Alliance Diversified Enterprises, Inc. for the Marquita Slope Interim Reconstruct project (Attachment 3). This project was initiated with an Emergency Coastal Development Permit through the California Coastal Commission in order to protect the Linda Lane Pump Station. The work consisted of installing caissons and tiebacks, and regrading the slope with geogrid reinforcement between soil layers. Other work included dewatering, removal of an existing soldier-pile wall at the toe of the slope, and installation of sub-drains.

An estimated summary of the construction expenditures related to this NOC is provided below:

Admin / Construction Management $ 29,578
Engineering Design 330,030
Legal 17,677
Hydrauger Construction 49,421
Landscape Architect 7,380
Construction Contract 2,363,193
Rail Pros Railroad Flagging 137,273
Total Construction Cost $ 2,934,552
This project is scheduled to be fully completed significantly lower th...