File #: 26-252   
Type: Resolution Status: Passed
File created: 5/19/2026 In control: City Council
On agenda: 6/16/2026 Final action: 6/16/2026
Effective date:    
Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE PICO / PRESIDIO DIP REPLACEMENT PHASE II, CIP PROJECT NO. 13411
Attachments: 1. Att. 1 - Resolution No. 26-115_PN 13411 Resolution.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - Staff Report dated December 9, 2025.pdf, 4. Att. 4 - Location Map.pdf
Department: Public Works
Prepared By: Jacob Ohana, P.E., Associate Civil Engineer

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE PICO / PRESIDIO DIP REPLACEMENT PHASE II, CIP PROJECT NO. 13411
body

Summary:
The City Council is being asked to consider adopting Resolution 26-115 (Attachment 1), accepting the Pico / Presidio DIP Replacement Phase II, and filing a Notice of Completion (Attachment 2).

Background:
On December 9, 2025, the City Council awarded a construction contract to Big Ben, Inc. for the Pico / Presidio DIP Replacement Phase II project (Attachment 3). This project was initiated to replace the existing water pipeline, which has reached the end of its useful life. The work consisted of the construction of a new eight-inch water main and its associated appurtenances, such as gate valves, fire hydrants, fire service connections, combination air release valves, and customer water service connections located at the Gateway Village Plaza. At the conclusion of the project, Big Ben, Inc. completed roadway repairs and restored affected concrete pedestrian and vehicular pathways.


A summary of the total construction expenditures is provided below:

Construction Management and Special Inspection $ 74,813
Construction 1,116,638
Total Construction Cost $ 1,191,451



Council Options:
* Adopt Resolution No. 26-115, which would accept the completed construction work for the Pico / Presidio DIP Replacement Phase II, CIP Project No. 13411.

* Adopt Resolution No. 26-115 with modifications.

* Continue the item with a direction to provide additional information.

Environmental Review/Analysis
Acceptance and filing of a notice of completion is not a project pursuant to CEQA. The work undertaken was previously determined to be c...