Legislation Details

File #: 26-338   
Type: Resolution Status: Passed
File created: 8/3/2026 In control: City Council
On agenda: 8/18/2026 Final action: 8/18/2026
Effective date:    
Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH GCI CONSTRUCTION, INC., FOR THE RESERVOIR 12 SITE IMPROVEMENTS, CIP PROJECT NO. 23403
Attachments: 1. Att. 1 - Resolution No. 26-138.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - Staff Report Constructin Award (3-17-2026).pdf
Submitted By: Public Works
Prepared By: Belgin Cuhadaroglu, P.E., Senior Civil Engineer

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH GCI CONSTRUCTION, INC., FOR THE RESERVOIR 12 SITE IMPROVEMENTS, CIP PROJECT NO. 23403
body

Summary:
The City Council is being asked to consider adopting Resolution 26-138 (Attachment 1), accepting the work performed by GCI Construction, Inc. for the Reservoir 12 Site Improvements, CIP Project No. 23403, and filing a Notice of Completion (Attachment 2).

Background:
On March 17, 2026, the City Council awarded a construction contract to GCI Construction, Inc., for the Reservoir 12 Site Improvements Capital Improvement Program (CIP) Project No. 23403 (Attachment 3). The project improved drainage to reduce localized flooding within the reservoir site during storm events and included the following: 201 linear feet of two 8-inch PVC drain pipes, asphalt concrete berms, 115 linear feet of retaining concrete curb, and a 12-inch square drainage inlet.













Before Construction After Construction

An estimated summary of the construction expenditures related to this NOC is provided below:

Project Management and Admin $ 10,500
Engineering Design 5,000
Construction Contract 140,658
Construction Management & Inspection 5,000
Total Construction Cost $ 161,158
Council Options:
* Adopt Resolution No. 26-138, which would accept the completed construction work for the Reservoir 12 Site Improvements, CIP Project No. 23403.

* Adopt Resolution No. 26-138 with modifications.

* Continue the item with a direction to provide additional information.

Environmental Review/Analysis:
The work undertaken was previously determine...