Legislation Details

File #: 26-346   
Type: Resolution Status: Passed
File created: 8/4/2026 In control: City Council
On agenda: 8/18/2026 Final action: 8/18/2026
Effective date:    
Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH ALLIANCE DIVERSIFIED ENTERPRISES FOR THE CALLE FRONTERA SEWER LIFT STATION SOIL STABILIZATION PROJECT, CIP PROJECT NO. 32201
Attachments: 1. Att. 1 - Resolution No. 26-139.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - Staff Report Constructin Award (1-20-2026).pdf
Submitted By: Public Works
Prepared By: Belgin Cuhadaroglu, P.E., Senior Civil Engineer

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR THE CONSTRUCTION CONTRACT WITH ALLIANCE DIVERSIFIED ENTERPRISES FOR THE CALLE FRONTERA SEWER LIFT STATION SOIL STABILIZATION PROJECT, CIP PROJECT NO. 32201
body

Summary:
The City Council is being asked to consider adopting Resolution 26-139 (Attachment 1), accepting the work performed by Alliance Diversified Enterprises, Inc. for the Calle Frontera Sewer Lift Station Soil Stabilization, CIP Project, PN 32201, and filing a Notice of Completion (Attachment 2).

Background:
On January 20, 2026, the City Council awarded a construction contract to Alliance Diversified Enterprises, Inc. for the Calle Frontera Sewer Lift Station Soil Stabilization (CIP) Project No. 32201 (Attachment 3). The project included the installation of a foundation support system consisting of caissons and grade beams to stabilize the existing building, minimize future structural movement, and prevent deterioration and cracking of the wet well structure.


An estimated summary of the construction expenditures related to this NOC is provided below:
Project Management & Admin $ 78,000
Geotechnical Feasibility Study 19,096
Engineering Design 104,250
Construction Contract 769,904
Construction Management & Inspection 109,200
Geotechnical Construction Support 69,598
Total Construction Cost $ 1,150,048
Council Options:
* Adopt Resolution No. 26-139, which would accept the completed construction work for the Calle Frontera Sewer Lift Station Soil Stabilization, CIP Project No. 32201.

* Adopt Resolution No. 26-139 with modifications.

* Continue the item with a direction to provide additional info...

Click here for full text