Legislation Details

File #: 26-424   
Type: Resolution Status: Passed
File created: 10/5/2026 In control: City Council
On agenda: 11/10/2026 Final action: 11/10/2026
Effective date:    
Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR CATCH BASIN AND STORM DRAIN IMPROVEMENTS AT AVENIDA PRESIDIO AND CALLE MIGUEL, CIP PROJECT NO. 12003
Attachments: 1. Att. 1 - Resolution No. 26-182.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - Staff Report dated February 3, 2026 (without attachments).pdf
Submitted By: Public Works
Prepared By: Jacob Ohana, P.E., Associate Civil Engineer

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR CATCH BASIN AND STORM DRAIN IMPROVEMENTS AT AVENIDA PRESIDIO AND CALLE MIGUEL, CIP PROJECT NO. 12003
body

Summary:
Resolution 26-182 (Attachment 1) represents the Notice of Completion (Attachment 2) for the Catch Basin and Storm Drain Improvements at Avenida Presidio and Calle Miguel, CIP Project No. 12003.

Background:
On February 3, 2026, the City Council awarded a construction contract to Torres Sanitation Systems Construction (TRS) to construct the improvements related to the Catch Basin and Storm Drain Improvements at Avenida Presidio and Calle Miguel (Attachment 3). The project scope and work included excavation and demolition of existing facilities, construction of new catch basins, construction of new drainage pipelines, manhole rehabilitation, and trench and pavement restoration.



During Construction
After Construction


An estimated summary of the project expenditures related to this Notice of Completion is provided below:

Project Management / Administration
$
12,500

Engineering Design

172,926

Construction Management/Inspection

68,580

Construction Contract

425,100

TOTAL
$
679,106


Council Options:
Adopt Resolution No. 26-182, which would accept the completed Catch Basin and Storm Drain Improvements at Avenida Presidio and Calle Miguel, CIP Project No. 12003.

Modify and adopt Resolution No. 26-182.

Continue the item with direction to provide additional information.

Environmental Review/Analysis:
This project was previously determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Class 1 (Existing Facilities, 14 CCR Section 15301) of the State CEQA Guidelines.

Fiscal Impact:
The total project cost is within the approved project budget of $750,000 from the Local Drainage Facilities Fund, Account ...

Click here for full text