Submitted By: Public Works
Prepared By: Masako Hennequin, P.E., Senior Civil Engineer
Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE A NOTICE OF COMPLETION FOR ALLEY PAVEMENT REHABILITATION PROGRAM, CIP PROJECT NOS. 16316, 15316, AND 12305
body
Summary:
The City Council is being asked to consider Resolution 26-116 and Notice of Completion for the Alley Pavement Rehabilitation Program (Attachments 1 and 2, respectively).
Background:
On February 17, 2026, the City Council awarded a construction contract to Eagle Paving LLC for the Alley Pavement Rehabilitation Program (Attachment 3). Eagle Paving LLC completed construction of the 20-ft wide alley at the 100 block of Avenida Del Mar, as shown on the Location Map (Attachment 4). The project consisted of grinding and repaving the destressed asphalt pavement, removing and replacing deteriorated pavement areas, and constructing 707 LF of new four-foot-wide concrete alley gutter in the middle of the alley to improve drainage.
A summary of the total construction expenditures is as follows:
Project Number
Budgeted Amount
Expenditure Amount
12305
$ 398,000
$ 153,088
15316
$ 100,000
$ 82,754
16316
$ 100,000
$ 84,999
Total Expenditures
$ 320,841
Council Options:
* Adopt Resolution No. 26-116, which would accept the completed Alley Pavement Rehabilitation Program, CIP Project Nos. 16316, 15316, and 12305.
* Modify and adopt Resolution No. 26-116.
* Continue the item with direction to provide additional information.
Environmental Review/Analysis:
This project was previously determined to be categorically exempt from the California Environmental Quality Act (CEQA) under Class 1 (Existing Facilities, 14 CCR section 15301) of the State CEQA Guidelines.
Fiscal Impact:
The total construction cost of $320,841 is within the approved budget for each respective project: Account Numbers 042-848-45300-000-16316, 042-848-45300-000-15316, and 042-848-45300-000-12305.