Title: CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE NOTICE OF COMPLETION FOR THE EMERGENCY SLOPE STABILIZATION REPAIRS AT CASA ROMANTICA, CIP PROJECT NO. 23502, APPROVING SUPPLEMENTAL APPROPRIATIONS IN THE AMOUNT OF $3,370,602 TO ACCOUNT NUMBER 001-481-43470-000-23502 AND AUTHORIZING THE CITY MANAGER TO APPROVE A CONTRACT AMENDMENT FOR ADDITIONAL WORK IN THE AMOUNT OF $3,310,602; AND POTENTIAL CITY COUNCIL DIRECTION ON PHASE 2B
Attachments: 1. Att. 1 - Resolution No.26-112.pdf, 2. Att. 2 - Notice of Completion.pdf, 3. Att. 3 - 2023 Staff Report.pdf
Submitted By: Public Works
Prepared By: Shawn Ryan, Deputy Public Works Director

Subject:
title
CONSIDERATION OF A RESOLUTION TO ACCEPT AND FILE NOTICE OF COMPLETION FOR THE EMERGENCY SLOPE STABILIZATION REPAIRS AT CASA ROMANTICA, CIP PROJECT NO. 23502, APPROVING SUPPLEMENTAL APPROPRIATIONS IN THE AMOUNT OF $3,370,602 TO ACCOUNT NUMBER 001-481-43470-000-23502 AND AUTHORIZING THE CITY MANAGER TO APPROVE A CONTRACT AMENDMENT FOR ADDITIONAL WORK IN THE AMOUNT OF $3,310,602; AND POTENTIAL CITY COUNCIL DIRECTION ON PHASE 2B
body

Summary:
The Emergency Slope Stabilization Repairs at Casa Romantica (CIP Project No. 23502) have been completed. Staff conducted consistent observation and inspection of the work, and the identified project can be considered by the City Council for acceptance. There remain additional tasks to complete before the comprehensive restoration project can be considered final. The City Council is being asked to provide direction for the final elements of the project.
The emergency work, performed by Alliance Diversified Enterprises, Inc., was initiated under the 2023 emergency declaration following a significant slope failure that impacted the Casa Romantica property. The contractor has completed all required stabilization activities, including installation of tiebacks and grade beams, geotechnical enhancements, grading, and associated protective measures.
Project closeout has been delayed due to ongoing coordination with the California Joint Powers Insurance Authority (CJPIA) to determine eligible reimbursement for unanticipated site conditions encountered during construction that could not have been identified prior to commencement of the project. These conditions required additional dewatering, expanded excavation, supplemental grout and shotcrete, storm-related slope protection, and emergency utility repairs. The detailed project costs are provided in the Discussion section of the report, under the Emergency Slope Cost Summary Matrix table...

Click here for full text